Cold test is not the first pass of "physical examination" for "cold" nuclear power plant

Column:Industry dynamics Time:2019-05-11
Recently, the Cold-state function test of Fuqing Unit 5, the world's first demonstration project of Hualong No. 1, has been successful. As China's third generation nuclear power with fully independent intellectual propert

Recently, the cold state function test of the fuqing no. 5 unit of "hualong no. 1", the world's first reactor demonstration project, was successfully carried out.As China's third-generation nuclear power plant with completely independent intellectual property rights, hualong 1 withstood the "high voltage" and passed a "big test" to test the unit's performance.This marked that the unit broke the first heap must drag "magic spell", early into the commissioning phase of the first step to win.



What is a cold test?Why is hualong one cold tested?Reporter of science and technology daily interviewed relevant personage about this.


Withstand "high pressure", reactor performance to withstand "big test"


If you compare a power station to a giant charging station, then hualong I is a huge nuclear fuel charging station -- nuclear power station.


One of the most important indicators for a nuclear power plant is safety.


Cold test, is short for cold function test, is a large comprehensive special plant commissioning test, the main purpose is to verify the circuit system and equipment and its various properties of auxiliary pipeline under high pressure, and pressure in each platform into the line of the primary system and auxiliary system related test, is the first time on the properties of the whole reactor comprehensive "examination".


It is also regarded as the first step to test the "nuclear power treasure", which can verify the integrity of each system, verify whether the normal pressure can be maintained in the state of exceeding the design benchmark, and test its performance and pressure resistance in excess of the design benchmark.


Whether the first reactor can advance as scheduled, the "physical examination" report is very critical.


Pressure is one of the first indicators to be evaluated in a cold test.The atmospheric pressure we are in daily contact with is 0.1 mpa, while the working pressure of the primary circuit of the nuclear power plant is 15.5 mpa.According to the design scheme, the design pressure of the primary circuit is about 17 mpa.But the cold test peaked at 22.3 megapascals, an area the size of the palm of a hand that would carry the weight of 10 fully loaded sedans.


People involved in China national nuclear corporation fuqing nuclear power co., LTD. (referred to as fuqing nuclear power co., LTD.) explained that the so-called peak pressure can be understood as the value of 200 kilometers per hour displayed on the dashboard of some cars, taking the cars we drive as an example.Design pressure is like the car we usually drive, the maximum speed can be up to 160 kilometers per hour, the work pressure of the primary road is 15.5 mpa, like the usual driving speed, such as 120 kilometers per hour.


It is worth mentioning that the pressure in cold test did not rise to 22.3 mpa in one step.After 16 hours of stepped-up pressure from 10 a.m. to 2 a.m. in the second sun ling, the main system pressure of the "hualong no. 1" fuqing no. 5 unit reached 22.3 mpa and stabilized for 10 minutes before passing the test.


The cold test will be followed by a long hot test


Literally, some people think cold trials are cold.In fact, the temperature of a cold test circuit is 35-70 degrees Celsius.


How is water heated without nuclear fuel?Relevant personage introduces, through blade agitate, advocate pump rotates in airtight space, kinetic energy converts heat energy, drive primary circuit to heat up.


The construction of a nuclear power plant has to go through several stages: preliminary preparation, civil construction, equipment installation and commissioning.After the cold test, the "hualong no.1" will be followed by hot test, critical test, platform test and performance test.


The so-called cold test is relative to the hot state performance test (referred to as hot test), it is also considered as the hot body of the hot test.After the cold test, the nuclear power plant is about to conduct a hot test.


Compared with the cold test temperature of 35-70 c, the hot test temperature is up to 300 c.


Different from the cold test, during the hot test, the staff will try their best to simulate the actual operating conditions of the nuclear power plant to verify whether the performance of the system is consistent with the design requirements and further verify the reliability of the nuclear power plant, including ensuring that the equipment cannot leak at room temperature and even cannot leak at high temperature.In addition, it is necessary to verify the reliability of the instrument and equipment under high temperature, check whether the temperature, pressure, flow, vibration, clearance and other measurement parameters meet the design value requirements.


In short, anything that may be affected by temperature must be checked, both at room temperature and at high temperature.In addition, many functions and safety of nuclear power plants need to be verified, including the natural circulation capacity of the passive core cooling system and the heat transfer capacity of the passive preheat and discharge heat exchangers


For this reason, compared with the cold test, the subsequent hot test will be a relatively long process, which is not a single test, but the sum of a series of tests.


It is understood that, according to the different units, the heat test less than a few days, more than a few months.During the thermal test, the operating procedures of the nuclear power station will be fully verified, the functions of the nuclear power plant will be fully inspected, and the team of operators in the nuclear power plant will be trained.


After the hot test, the material will be loaded. According to the plan, the first batch of "hualong no.1" fuqing nuclear power plant, the world's first reactor, will be loaded for the first time by the end of this year.If the 62-month construction period is followed, unit 5 is scheduled to be officially connected to the grid in July next year.


Big data and sand table deduction realize risk control in advance


Since May 7, 2015, when the world's third generation nuclear power units under construction got stuck in the "quagmire", the world's first reactor demonstration project hualong I has been progressing smoothly, and construction according to the planned schedule has become an important label.


"Hualong I is a complex systems engineering, an innovation process from scratch."Xing ji, chief designer of the "hualong no.1" project of China national nuclear corporation, especially introduced that one of the key problems of the demonstration project is to complete the construction drawing design of the first reactor on schedule.


Through the continuous promotion of "Internet +", CNNC combines the design of nuclear power, application software integration with the Internet and other technologies to establish a long-distance integrated collaborative design platform. Through network connection and various terminal devices, multiple design units nationwide carry out long-distance collaborative design on the same platform.The number of collaborative design platform terminals reaches 500 and can be expanded as required.


On this platform, nearly 1,000 "hualong no. 1" site engineers and designers realize timely communication and sharing of information, speed up the transmission of design data, reduce the repetition of design exchange process, and effectively improve the design efficiency.


While carrying out the design work, CNNC made full use of the efficiency and convenience of the design information platform to timely summarize the technical problems encountered in the construction of the demonstration project into the big data in the design field, which was not only fed back to the equipment manufacturer and the project builder, but also passed on to the subsequent nuclear power projects.


"This has laid the technical foundation for the standardized design and mass construction of hualong no. 1 nuclear power project, and improved the economy of construction and operation."The xing said.


Starting from 300,000 kw, hualong I is a new product introduced, absorbed and created by China's nuclear power research and development.The hualong 1 has a design life of 60 years, with 177 reactor cores and 18 months of refueling.Among them, the independent intellectual property rights cover the design, fuel, equipment, construction, operation, maintenance and other fields, and has independently developed special software for nuclear power, forming a complete intellectual property system, is the only three generation model that can be independently exported in China.As the world's first demonstration reactor project, the localization rate of construction equipment for unit 5 of fuqing nuclear power plant is no less than 85%, and more than 100 sets of "three new" equipment have been purchased and installed.


Chen guocai, general manager of fuqing nuclear power plant, told reporters that the constantly optimized project management mode and innovative project management mode have ensured the steady progress of demonstration project construction and provided valuable practical experience and reference basis for the subsequent batch construction of "hualong no.1".


In the first reactor construction, the construction team used sand table for simulation and deduction for the first time in China.For example, in the design field, six typical design organization and management tasks, such as DCS capital raising planning for power plant, are selected for sand table deduction.


According to Chen guocai, by summarizing the basic facts, testing the management team's management knowledge, experience and problem solving ability, and analyzing and predicting the development trend of the project stage, the goal of advance management and risk control can be achieved.


久久精品电影网 | 曰本三级在线 | 日韩欧美精品一区二区三区经典 | 草久电影 | 午夜10000 | 欧美激情片在线观看 | 99久久精品国产一区二区成人 | 亚洲欧洲xxxx | 国产成人免费在线观看 | 超碰在线94 | 久久精品中文视频 | 日韩av黄 | 久久久久久国产精品999 | 五月天婷婷视频 | 久久96国产精品久久99漫画 | 波多野结衣电影一区二区 | 久章草在线 | 国产麻豆精品在线观看 | 久久免费视频在线 | 欧美日本不卡 | 国产精品专区在线 | 日本三级国产 | 日本久久精品视频 | 又黄又刺激的网站 | 日日躁你夜夜躁你av蜜 | 欧美一区二区在线看 | 国产成人精品久久亚洲高清不卡 | 五月婷婷激情六月 | 人人澡人人爱 | 日韩激情影院 | 国产精品久久99精品毛片三a | 91香蕉视频污在线 | 成人蜜桃视频 | 国产二区av| 久久久久久国产一区二区三区 | 婷婷综合亚洲 | 99热9| 黄色的网站免费看 | 一级免费黄色 | www黄在线 | 国产资源站 | 激情xxxx | 欧美激情h| 日韩精品欧美专区 | 婷婷丁香综合 | 国产日女人 | 免费看黄色大全 | 草在线| 97精品国产97久久久久久 | 久久久午夜剧场 | 久精品视频在线观看 | 国产三级午夜理伦三级 | 天天草天天爽 | 欧美精品久久久久 | 中文字幕中文字幕在线中文字幕三区 | 美国av大片 | 国产精品免费人成网站 | 天天操 夜夜操 | 欧美国产日韩一区二区 | 成人久久18免费网站 | 国产一级a毛片视频爆浆 | 亚洲激情综合 | 人人爱人人添 | 激情综合中文娱乐网 | 欧美日一级片 | 中文字幕你懂的 | 最近中文字幕大全中文字幕免费 | 亚洲黄色av网址 | 超碰人人国产 | 热re99久久精品国产99热 | www.888av| 永久免费的av电影 | 日韩 在线| 黄色特级一级片 | 久久久久久久影视 | 久久综合之合合综合久久 | 91大神精品视频在线观看 | 天天干夜夜想 | 亚洲九九九在线观看 | 久久久免费在线观看 | 黄色片网站av | 色视频国产直接看 | 亚洲国产精品久久久久久 | 国产午夜精品理论片在线 | 午夜免费福利视频 | 一区二区中文字幕在线观看 | 天天曰天天爽 | 99精品久久久久久久久久综合 | 亚洲少妇自拍 | 久久夜夜夜 | 最新99热 | 91九色porn在线资源 | 久草精品免费 | 亚洲精品国产欧美在线观看 | 中文字幕韩在线第一页 | 99久久久久久国产精品 | 欧美精品v国产精品 | 久久爱综合 | 久久精品观看 | 欧美日韩亚洲在线观看 | 99视频国产在线 | 欧美日韩精品国产 | 国产最顶级的黄色片在线免费观看 | 国产成人三级在线观看 | 免费网站黄 | 亚洲精品99久久久久久 | 丁香电影小说免费视频观看 | 久久久久一区二区三区四区 | 欧洲亚洲精品 | 精品久久久999 | 一区二区三区四区在线 | 国产精品亚州 | 成人app在线免费观看 | 黄色com | 五月天激情综合 | 国产美女网站视频 | 欧美一级免费黄色片 | 一区二区三区四区五区在线视频 | 国产91对白在线 | 人人网人人爽 | 欧美日本高清视频 | 天天射日| 欧美成a人片在线观看久 | 久久久久久久精 | 中文字幕在线观看视频一区 | 97精品久久人人爽人人爽 | 日日夜夜精品视频天天综合网 | 高潮久久久久久 | 国产精品久久久一区二区三区网站 | 国产一区二区视频在线 | 97超碰超碰久久福利超碰 | 免费观看91 | 精品在线视频观看 | 国产精品18毛片一区二区 | 国产日本在线播放 | 亚洲三级黄色 | 97超碰网 | 久热久草| 美女视频黄在线观看 | 久草视频免费观 | 国产精品丝袜在线 | 免费视频你懂的 | 亚洲精品日韩av | 永久免费看av | 国产在线观看av | 奇米影视8888在线观看大全免费 | 国产人免费人成免费视频 | 久久露脸国产精品 | 在线视频18在线视频4k | 91九色免费视频 | 国产精品第52页 | 国产精品久久久久久一区二区三区 | 精品免费一区二区三区 | 久久玖 | 91刺激视频 | 欧美国产日韩在线观看 | 国产亚洲字幕 | 天天性天天草 | 欧美日韩国产伦理 | 国产精品久久久久久久久久新婚 | 人人搞人人搞 | 成人小视频免费在线观看 | 久草在线视频免赞 | 色97在线| 69性欧美| 一区二区 久久 | 精品国产一区二区三区不卡 | 国产成人精品一区二区在线观看 | 黄色资源在线观看 | 97超碰超碰久久福利超碰 | 国产美女精品视频免费观看 | 国产毛片aaa| 色99色| 国内精品久久久精品电影院 | 国产视频1 | 久久这里只有精品视频99 | 六月色婷婷 | 成人午夜精品久久久久久久3d | 国产一区二区三区免费视频 | 欧美日韩一级视频 | 久久久国产影院 | 国产999精品久久久影片官网 | 日日夜夜噜 | 欧美中文字幕第一页 | 97香蕉久久超级碰碰高清版 | 在线看一区二区 | 在线小视频 | av在线播放快速免费阴 | 深爱婷婷激情 | 日b视频国产 | 亚洲精区二区三区四区麻豆 | 日韩网站免费观看 | 国产小视频你懂的在线 | 久久污视频 | 久久久久国产精品免费免费搜索 | 日韩大片在线免费观看 | 国产亚洲情侣一区二区无 | 色视频网站在线观看一=区 a视频免费在线观看 | 亚洲第一av在线 | 精品字幕在线 | 伊人久久电影网 | 五月综合色| 日本精品一区二区在线观看 | 国产中文字幕在线视频 | 国产三级精品三级在线观看 | a黄色片 | 日日夜夜天天久久 | 精品久久99 | 免费在线观看亚洲视频 | 国产免费高清视频 | 又黄又爽的视频在线观看网站 | 国产一区二区视频在线播放 | 在线免费高清视频 | 亚洲视屏| 成人免费网站在线观看 | 精品1区2区3区 | 久久久久久高潮国产精品视 | 久久久久亚洲精品国产 | 国产麻豆精品一区 | 91香蕉视频 mp4| 国产香蕉视频在线观看 | 友田真希av | 伊人视频 | 中文字幕高清在线 | 97福利社| 欧美激情视频在线观看免费 | 久久超级碰 | 欧美俄罗斯性视频 | 国内精品视频在线播放 | 波多野结衣一区二区 | 亚洲精品欧美专区 | 欧美精品久久久久久久久老牛影院 | 91免费观看视频网站 | 久久久久国产精品www | 亚洲精品国产精品久久99热 | 久久久国产精品视频 | 国产五月天婷婷 | 西西444www| 99久久精品视频免费 | 欧美日韩免费在线视频 | 91福利国产在线观看 | 午夜精品一二三区 | 久草在线最新免费 | 欧美极品少妇xbxb性爽爽视频 | 亚洲精品女人 | 国产91精品看黄网站在线观看动漫 | 欧美一二三在线 | 狠狠干狠狠艹 | 国产精品第7页 | 日韩欧美国产免费播放 | 精壮的侍卫呻吟h | 国产在线播放不卡 | 丁香六月国产 | 亚洲精品成人网 | 久久成电影| 色噜噜狠狠狠狠色综合久不 | 国产黄色精品 | av网站在线免费观看 | 麻豆成人小视频 | 日本动漫做毛片一区二区 | 91污视频在线| 天天摸天天舔天天操 | 成年人网站免费在线观看 | 九九热在线精品视频 | 18+视频网站链接 | ,午夜性刺激免费看视频 | 日韩在线视频观看 | 亚洲精品国产品国语在线 | 国产成a人亚洲精v品在线观看 | 91精品爽啪蜜夜国产在线播放 | 免费高清在线视频一区· | 91在线资源 | 黄色一级大片在线免费看国产一 | 色婷婷av一区 | 免费又黄又爽的视频 | 性色av一区二区三区在线观看 | 丁五月婷婷 | 午夜视频久久久 | 日韩成人高清在线 | 天天操天天干天天摸 | 国内精品视频在线播放 | 日韩在线观看一区二区 | 97超碰福利久久精品 | 亚洲欧洲精品久久 | 久久精品综合视频 | 天天操天天综合网 | 久久久久久麻豆 | 精品伦理一区二区三区 | 九九热免费在线观看 | 六月激情| 91桃色免费观看 | 亚洲成人二区 | 91精品国产91热久久久做人人 | 69国产盗摄一区二区三区五区 | 五月天婷婷在线视频 | 免费av在线网 | 久久欧美视频 | 国产流白浆高潮在线观看 | 五月天久久久久 | 天天干天天干天天操 | 天天操天天操天天干 | 精品欧美日韩 | 十八岁免进欧美 | 中文久草 | 国产精品99久久久久久武松影视 | 伊人国产视频 | 九色激情网 | 免费看国产精品 | 亚洲人成免费网站 | 99色视频| 97人人爽 | 久久99网 | 黄色一区二区在线观看 | 国产免费视频一区二区裸体 | 亚洲欧美日韩一区二区三区在线观看 | 亚洲精品videossex少妇 | 色综合欧洲 | 亚洲高清色综合 | 99精品欧美一区二区三区 | 久久久久久草 | 国产在线精品一区二区不卡了 | 欧美日高清视频 | 91av电影网 | 韩国av电影网 | 国产日韩精品久久 | 中文字幕亚洲欧美日韩 | 五月天天色| 日韩在线观看视频在线 | 香蕉视频在线观看免费 | 99视频在线免费播放 | 国产中文字幕av | 黄色国产高清 | 在线成人国产 | 精品国产欧美一区二区 | 韩国一区在线 | 九九久久成人 | 99精品电影 | 国产91精品一区二区 | 日本资源中文字幕在线 | 色a网| 最新av在线网站 | 婷婷亚洲最大 | 亚洲五月 | 蜜臀aⅴ国产精品久久久国产 |